Implementation Organization : Energy Conservation Research and Development Center (ENERTEAM)
Country : Viet Nam
Project Area : Energy and air
NetRes : IGES
Duration of Project : 18 months
Status : Ongoing
Summary
This project aims to develop a showcase in Viet Nam on a new energy technology, the rice husk gasification, which can provide the avoidable Green House Gases, through a new model of energy service business under the type of B.O.T. This is a very new concept in energy service sector in Viet Nam.
Key Activities
Activity 1: Feasibility study
Objectives:
- Explain to management board of brick making company on the project.
- Assisting this board to make decision.
Expected results:
- Feasibility report document.
Description:
Owners of tunnel brick making kiln often are companies with a certain scale. They obviously have management board, so explaining to this board for assisting decision making is very necessary. Moreover, according to the law, particularly concerning to company’s fixed asset issues and taxation, feasibility study (according to the VN law, the terminology is Investment Report) is also needed. Therefore, feasibility study report, with technical, fuel supply security and financial analysis is very important.
Activity 2: Set up financial model agreement
Objectives:
- Set up showcase on the financial model based on B.O.T. concept.
Expected results:
- Payment agreement document
Description:
Based on the feasibility study and discussion with the brick company on the financial model, the payment agreement or contract will be signed. One thing to be notable in the agreement is the whole model, comprising equipment and payment issues will be delivered to a third party, a full business ESCO.
Activity 3: Equipment ordering
Objectives:
- Equipment purchasing and infrastructure construction
Expected results:
- Infrastructure available
- Equipment purchasing document
- Equipment delivery from supplier to the site
Description:
Based on equipment specifications identified during the feasibility study, they will be sent to equipment fabricant for ordering. The South-South collaboration will be reinforced by looking at fabricants from Asian countries first.
During the equipment manufacturing, few key staffs will be sent to the fabricant for training on installing, functioning and operation.
At the same time, infrastructure, such as civil works, will be done for being ready for the equipment installing.
Activity 4: Equipment installing and functioning
Objectives:
- Put the gasification facilities into operation.
- Testing and adjust the new financial model.
Expected results:
- The Equipment put into operation with commissioning data sheet.
Description:
All equipment will be installed and put into commissioning. After the technical commissioning and stable operation, the financial model will be also put into testing operation during three months for adjusting. This is a very new financial model in energy service activities in Viet Nam, therefore, during the financial testing operation; all problems will rise up and be resolved.
Activity 5: Model delivery to full business organization.
Objectives:
- Showcase of the full business possibility of energy service under the form of B.O.T in Viet Nam.
Expected results:
- The whole model will be managed by an ESCO with full business basis, with delivery document
- Payment receipts on the payment from customer.
Description:
The full business model can be a showcase if it is managed by a full business organization, a real ESCO. Therefore the whole model will be delivered to a full business company. The successfulness of this ESCO to manage this model after delivery is a success factor of this project.
Moreover, ENERTEAM is a research & development center. Its role is to develop pioneer models, demonstrate the viability of these models in both technology and financial aspects, but not full business making. Therefore, the success of the ESCO is the success of the showcase.
Thus, the whole model, including technical and financial, will be deliver to a real ESCO with business basis.
Activity 5: Result campaigning workshop
Objectives:
- This is a showcase, so the experience diffusing is indispensable. Therefore, a workshop for sharing experience on this model will be set up.